NIPSCO said Friday it will delay work to close five coal ash ponds at its lakeshore generating station until spring 2021.

Several organizations had requested the delay because of concerns that excavation and transportation of the coal ash from the Michigan City Generating Station to a landfill at the company's R.M. Schahfer Generating Station in Wheatfield could contribute to an increase in air pollution, which in turn could lead to a higher COVID-19 mortality rate in affected communities.

The LaPorte County Branch of the NAACP and Just Transition NWI said in a news release that NIPSCO's willingness to address community concerns was important and the delay "has been acknowledged as a necessary step within the closure process."

The community and environmental groups said NIPSCO delayed its plans to remove 170,600 cubic yards of coal ash from five ponds at the Michigan City plant days after the NAACP and Just Transition NWI submitted a petition to the Indiana Department of Environmental Management urging NIPSCO to delay the removal until after the pandemic is over.

The groups said they, along with Hoosier Environmental Council, Save the Dunes and Earthjustice, have demanded NIPSCO implement much stronger public safety measures than currently proposed when the time is appropriate for the removal process to move forward.

NIPSCO spokesman Nick Meyer said community input is an important part of the process, but the company's decision to shift the timing for the removal process was not related to the coronavirus pandemic.

"As part of our normal operations today, we safely transport 50,000 tons of ash material each year from Michigan City to our Schahfer facility," Meyer said. "This work is very similar and the material will be transported to the same location. Constant oversight, inspections and dust-control measures will be in place to ensure the work is being conducted safely."

NIPSCO said it will remain on track to complete the proposed ash pond work ahead of a 2023 deadline while also advancing other goals, including electric and gas modernization projects.
User is offlineProfile CardPM
Go to the top of the page
+Quote Post

Reply to this topicStart new topic
1 User(s) are reading this topic (1 Guests and 0 Anonymous Users)
0 Members:

 



Lo-Fi Version Time is now: 28th March 2024 - 05:45 PM

Skin Designed By: neo at www.neonetweb.com