The latest construction update from NICTD
QUOTE

"MICHIGAN CITY – 10TH AND 11TH STREET AREA
Comcast is anticipating work at Sheridan Ave to be completed by April 1. Additional aerial cable and underground work between Lafayette and Phillips streets should be completed by April 1. Comcast utility work may involve short-term street closures, travel lane restrictions, and flagging.

NIPSCO’s gas team should complete work on gas service lines around Willard and 10th St. by mid-March.
NIPSCO’s electric team should complete work at Sheridan Ave by the end of April.

Real estate acquisition is complete.

Demolition of structures is 95% complete to date in Michigan City. Properties are being boarded up and managed by NICTD’s contractor. All of the residential structures will be demolished by the end of March.
The historic 11th Street station has been demolished and foundation removal is complete. The block is fenced and portions of the sidewalk are closed to allow for continuing work. Pedestrians must use the south side of 11th Street.

Construction on 11th Street began February 28, 2022, which included a full closure of 11th St itself. The project provides weekly updates to Michigan City Mayor Duane Parry and city staff including police, fire and county emergency response teams, to ensure everyone is prepared for upcoming work. Michigan City residents can expect north/south street closures that progress westward as construction advances, with signage indicating which streets will be closed. Residents, businesses and other property owners are also being notified of any work that will impact ingress/egress for their particular site.
Additional road closure details:

On February 28, 2022, Walsh/Herzog (WH) closed 11th Street from Chicago Street to Michigan Boulevard. This closure is required to build the two new South Shore Line tracks, create an isolated railroad right-of-way, and improve public safety along 10th and 11th streets.

Pursuant to the 2016 Agreement with Michigan City, the intersection of 11th Street with the following streets will be permanently closed and configured into cul-de-sacs in accordance with the final, approved design.

- Elston Street
- Manhattan Street
- Buffalo Street
- Pine Street
- Spring Street
- Cedar Street
- York Street
- Maple Street

The intersection of 11th Street with the following streets will only be closed as required to construct the work across the intersections.

- Chicago Street
- Ohio Street
- Wabash Street
- Washington Street
- Franklin Street
- Lafayette Street
- Oak Street

It is currently anticipated that two closures of each of these intersections will be required with each closure lasting approximately two to three weeks.

To maintain traffic flow in the north south direction past 11th Street, the following constraints will be implemented by Walsh/Herzog:

Tennessee St will remain open when Ohio St is closed until the Ohio Street crossing is re-opened.
The intersections of Wabash St, Washington St, and Franklin St will only be closed one at a time.
The intersections of Lafayette St and Oak St will also only be closed one at a time.
Michigan Boulevard will remain open throughout the duration of the project.

The intersections at 11th and Franklin were converted from a stoplight to a stop sign configuration during construction. Construction on 10th Street will occur to the south of the existing roadway, where the two new tracks will be installed. At the completion of the work, the current tracks down 10th Street will be removed and the roadway repaired.

Larson-Danielson Construction was awarded the contract to remove the façade from the historic station building on 11th and Franklin streets. It has been removed, and is being repaired and stored for future re-erection onto the large 11th Street Station and parking structure. The City is currently working with Flaherty & Collins, a developer, to evaluate alternative Transit Oriented Development (TOD) options for the block bounded by 10th, 11th, Franklin and Pine. Plans for that development are in progress. Questions should be directed to the City of Michigan City for the TOD effort.

NICTD has provided the City of Michigan City with an emergency response contact list. Emergencies should be reported using 911. "
User is offlineProfile CardPM
Go to the top of the page
+Quote Post
 
Reply to this topicStart new topic
Replies
Southsider2k12
post Sep 19 2022, 02:02 PM
Post #2


Spends WAY too much time at CBTL
******

Group: Admin
Posts: 16,409
Joined: 8-December 06
From: Michigan City, IN
Member No.: 2



Changes coming around the 26th to the 11th street corridor.

QUOTE
MICHIGAN CITY – 10TH AND 11TH STREET AREA
Track construction is underway at the east end of the Double Track project in Michigan City (Michigan Blvd is eastern project limit).

Construction on 11th Street began February 28, 2022, which included a full closure of 11th St itself that will run through mid-November 2022. Michigan City residents can expect north/south street closures that progress westward as construction advances, with signage indicating which streets will be closed and when. The site of the future 11th Street Station and Transit Oriented Development is the block bounded by 10th, 11th, Franklin and Pine Streets. That block is currently fenced and portions of the sidewalk are closed to allow for continuing work.

For full details on the future road conditions after construction, click here.

Installation of the overhead catenary poles is in progress in the Right of Way south of 10th St.

The intersections at 11th and Franklin were converted from a stoplight to a stop sign configuration during construction. Construction on 10th Street will occur to the south of the existing roadway, where the two new tracks will be installed. At the completion of the work, the current tracks down 10th Street will be removed and the roadway repaired.

Willard Ave is closed from July 20 through September 26 to construct the new north track through this intersection.

Sheridan Ave at 10th Street will close on 9/26 for approximately 40 days.

Lafayette Street will close on 9/26 for approximately 14 days.

Wabash Street closed on August 4 to construct the new north track through the intersection and is expected to re-open around September 26. Franklin Street and Washington Street remain open during the Wabash Street closure to provide north-south access across 11th Street. Road closure information will be updated as work progresses.

After Wabash Street opens, Washington Street will close for approximately 19 days. During the Washington Street closure Franklin Street and Wabash Street will remain open to provide north-south access across 11th Street. Road closure information will be updated as work progresses.

NICTD has provided the City of Michigan City with an emergency response contact list. Emergencies should be reported using 911.
User is offlineProfile CardPM
Go to the top of the page
+Quote Post

Posts in this topic
Southsider2k12   NICTD construction update   Mar 22 2022, 09:11 AM
Southsider2k12   Latest updates   Apr 27 2022, 03:41 PM
Southsider2k12   MICHIGAN CITY – 10TH AND 11TH STREET AREA Comcas...   May 5 2022, 10:56 AM
Southsider2k12   RE: NICTD construction update   May 11 2022, 10:00 AM
Southsider2k12   RE: NICTD construction update   May 25 2022, 02:11 PM
Southsider2k12   https://chicagocrusader.com/holcomb-announc...-tra...   Jun 30 2022, 09:28 AM
Southsider2k12   RE: NICTD construction update   Jul 6 2022, 03:24 PM
Southsider2k12   https://www.nwitimes.com/news/local/laporte...d55a...   Jul 21 2022, 09:48 AM
diggler   https://www.nwitimes.com/news/local/laporte...d55...   Jul 29 2022, 12:57 PM
Southsider2k12   MICHIGAN CITY – 10TH AND 11TH STREET AREA Track ...   Sep 14 2022, 01:43 PM
Southsider2k12   Changes coming around the 26th to the 11th street ...   Sep 19 2022, 02:02 PM
Southsider2k12   https://www.nwitimes.com/business/local/com...medi...   Oct 25 2022, 07:01 AM
Southsider2k12   Double track construction is on track to be done i...   Jan 31 2023, 10:56 AM
Southsider2k12   Throughout 2023 the following work is expected to ...   Mar 9 2023, 03:18 PM
Southsider2k12   https://www.southbendtribune.com/story/news...rs/7...   May 1 2023, 12:01 PM
Southsider2k12   RE: NICTD construction update   May 2 2023, 08:44 AM
Southsider2k12   Walsh Construction has provided the City of Michig...   Jun 5 2023, 03:25 PM
Southsider2k12   MICHIGAN CITY – 10TH AND 11TH STREET AREA Track...   Jun 20 2023, 09:32 AM
Southsider2k12   TOWN OF PINES AREA?? NICTD owns the property just...   Jul 11 2023, 03:07 PM
Southsider2k12   RE: NICTD construction update   Jul 26 2023, 09:01 AM
Southsider2k12   RE: NICTD construction update   Aug 14 2023, 01:56 PM
Southsider2k12   RE: NICTD construction update   Aug 24 2023, 10:02 AM
Southsider2k12   https://www.chestertontribune.com/articles/...from...   Sep 7 2023, 11:31 AM
Southsider2k12   RE: NICTD construction update   Sep 26 2023, 06:44 AM
Southsider2k12   MICHIGAN CITY – 10TH AND 11TH STREET AREA 11th ...   Nov 17 2023, 09:11 AM
Southsider2k12   Double Track Update: We're nearing the finish ...   Feb 29 2024, 12:25 PM
Southsider2k12   https://www.wndu.com/2024/03/01/double-trac...lmos...   Mar 21 2024, 10:25 AM


Reply to this topicStart new topic
2 User(s) are reading this topic (2 Guests and 0 Anonymous Users)
0 Members:

 



Lo-Fi Version Time is now: 28th March 2024 - 05:11 AM

Skin Designed By: neo at www.neonetweb.com